A collection of structures along Fayette Avenue have been demolished as construction along the roadway continues into its second phase.
Plans to demolish a series of additional buildings, including the old Gabby Goat Pub and the old A1 Liquors location, are being coordinated between IDOT and the city of Effingham.
The city will be involved in relocating its existing utility lines off both sides of the roadway once all the necessary buildings are demolished according to City Administrator Steven Miller.
“Everything on those sides of the road [Fayette Avenue] is essentially going to get demolished too,” Miller said. “And then they’ll (IDOT) have a contract to widen the road.”
IDOT said that the project is necessary due to the roadway’s narrow widths and the lack of left-turn lanes throughout the section. In the past, the high traffic volume along Fayette Avenue has resulted in a “high number of crashes in the area,” according to IDOT.
Drivers can expect periodic lane closures, arrow boards, barrels and signs to be in place along the roadway to guide motorists through the work zone. The construction is part of a larger $56 million Fayette Avenue improvement project.
The improvements are warranted by IDOT’s capital program called Rebuild Illinois, passed in June of 2019. According to a Sept. 22 IDOT press release, the project is investing $25.6 billion of road improvements statewide.
The city expects the construction on Fayette Avenue to be complete between the months of February and June of 2027.