TRAVERSE CITY — Motorists on South Airport Road are urged to plan ahead next week as crews begin construction to replace a sewer force main that failed earlier this year near Logan’s Landing, prompting closures of the road’s westbound lanes.
Garfield Township trustees unanimously approved a $1.77 million bid from Team Elmer’s for the project during their Oct. 27 meeting, clearing the path for work to begin on Nov. 9.
Elmer’s crews estimate the project will take approximately three weeks to complete.
Gourdie-Fraser Inc. — the engineering firm under a nearly $187,000 contract with the township — expedited the design process to meet the urgent timeline, Principal and Project Manager Jennifer Graham said.
Traffic interruptions are expected during the construction as crews complete drilling and installation.
“The whole goal with this project to be trenchless is to be outside the road,” Graham told township trustees last week, explaining lane closures are expected.
Roughly 1,400 feet of new pipe will be replaced and buried 10-feet deep following the current main’s failure on Aug. 25. A four-foot crack along the bottom of the 10-inch high-density polyethylene (HDPE) pipe — originally placed in the 1970s — spilled thousands of gallons of sewage water underneath South Airport Road’s asphalt, west of Park Drive, and into the Boardman-Ottaway River that feeds into Boardman Lake.
The sanitary force main transfers sewage from Pump Station No. 2, according to bid documents included with the township’s agenda. The system provides service to approximately 2,500 customers, measuring a peak hourly flow of 700 gallons per minute. After the replacement, the future capacity will increase to up to 1,400 gallons per minute.
“We are putting a larger one in,” Graham said, noting the goal is to exceed the industry’s current standards. “We want to make sure that we have added redundancy capacity to exceed 20-, 30-, 40-year growth.”
Coordination between the township and Grand Traverse County Road Commission officials addressed any potential concerns with the construction and repairing damaged asphalt.
The work was bundled into a singular project but separated in two divisions to allow for flexibility during the open bidding process. The county’s Department of Public Works also coordinated on the project’s plan.
“If we’re going to do this, we’re going to do this once,” Graham said. “We’re trying to implement as much protocols and redundancy as we can.”