DANVILLE — While normally the city council meets the first and third Tuesday of every month, this week they will meet on Wednesday because of the 2026 midterm elections on Tuesday.
The public works committee discussed the draft tax levy and 2027-28 budget last week. Much of the conversation was about the Midtown Tax Increment Financing District (TIF) reserves, and how demolition costs are covered.
The budget discussion also included a proposed $14.5 million infrastructure expenditure for the Bowman and Seminary streets project.
“The Midtown TIF. It looks like we’re pulling $102,000 out of reserves for that,” Alderman Doug Ahrens said. “What are our current payouts? Is the $102,000 necessary to meet the current payment agreements, or is that anticipated as a special project?”
Comptroller Alyssa Sweeten said that amount is for a ‘special project.’
Public Works Director David Ruwe said the city is receiving grant funding to help cover the Bowman and Seminary streets project.
“We’ve got the SS4A grant, which is about $10 million of that,” Ruwe said. “That’s the total project value, but that projects a number of other big expenditures.”
Ruwe added they are not anticipating any overlay plans for the project.
The committee also approved using state motor fuel tax funds for the construction and engineering services for the Voorhees Street bridge work.
When it came time to discuss the budget, Ahrens did have a few questions.
Ahrens questioned whether the $450,000 budget for animal control was accurate.
“I know we worked out a situation where they were to just bill us the way the agreement originally stated,” Ahrens said. “Is that tracking, and is that the ongoing agreement now with the county?”
Sweeten said, “At least for the agreement we have currently, it is tracking to be the $450,000.”
“We’ve been working really hard to make sure that everything is properly accounted for across, and that it’s as transparent as possible as to our expenses,” Mayor Rickey Williams Jr. said.
Ahrens also brought up demolitions.
“Well, it should still be the goal,” Ahrens said about the number of houses up for demolition. “We still need 500 to 700 houses going down, and it should get done in the next five years. And so, once again, do we know the numbers that are out there? … Do we understand the scope of the demolition program and the problem? And is it 500 structures? Is it 700? What is the number?”
Williams said there would be more structures demolished if funds had not been put towards other areas.
“We could have had twice as many done by now because, if you’ll recall, originally when the administration proposed the additional half a percent in sales tax, all of that was to go to demolitions,” Williams said. “Unfortunately, it was vigorously opposed by individuals that half of that then be going to stormwater instead. So if we were very serious about demolitions, we could have had twice as many done by now.”
Ahrens asked Williams if he could give an estimated number of houses that need demolition, but Williams said, “I know how many are on our list…”
Ahrens said he believes the last list ranged from 200-250 structures, but anticipates there are likely double that amount.
“There’s probably more than 500 out there,” Ahrens said. “And so I just hoped with nine inspectors we would understand the scope of the problem, so that if we need to allocate more money that way today… “
Ahrens believes that 120 structures demolished “should be our goal today.”
Council will meet at 6 p.m. on Wednesday in the City Council Chambers at the Robert E. Jones Municipal Building, 17 W. Main Street. You can also stream the meetings on their YouTube page.